Naval Facilities Engineering Systems Command

NAVFAC Southwest Awards $42.6 Million for Camp Pendleton 1st Marine Division Operations Complex

03/04/21 10:08 AM

SAN DIEGO – Naval Facilities Engineering Systems Command (NAVFAC) Southwest awarded Harper Construction Company Inc., of San Diego, a $42.6 million task order, Feb. 18 in San Diego, for the design and construction of a division operations complex at Marine Corps Base (MCB) Camp Pendleton.

“We’re excited about executing this recapitalization project for one of our nation’s most renowned warfighting commands,” said Capt. Mike Oestereicher, NAVFAC Southwest commanding officer. “This project replaces numerous facilities that are 70-80 years old with a state-of-the-art modernized complex to meet the 21st century requirements of the 1st Marine Division and the United States Marine Corps.”

The task order is the first issued on a new multiple award construction contract with a total capacity of $2.5 billion. Harper Construction Company, Inc. was one of multiple companies to submit proposals for the task order.

“Award of this project represents a significant milestone for maintaining the division at its most ready state,” said Lauren Alarie, NAVFAC Southwest senior project manager. “The project consolidates critical functions for both the Division and Battalion Headquarters and replaces their existing outdated and fragmented facilities with a new state-of-the-art campus complex. The Project Development Team inclusive of all stakeholders and supporting commands is looking forward to working with Harper Construction Co. to develop a modern, integrated design and ensure quality construction through to completion.”

Harper Construction Company Inc. will demolish nine single story concrete buildings and nine temporary trailer buildings, and design and construct a new 58,931 square foot Division Command Post Headquarters, 11,538 square foot Battalion Command Post Headquarters, and parade field. The project includes cybersecurity features, paving and site improvements including parking areas, roadways, curbs, gutters, sidewalks, landscaping, trash enclosures and signage. The current “White House” command post will remain as-is to preserve the historic and honored nature of the building and thus is not included in the scope of this awarded contract.

“The P1130 project will allow for the creation of a facility that integrates several elements of the 1st Marine Division’s command and control structure under one roof,” said Maj. Gen. Roger B. Turner Jr., 1st Marine Division commanding general. “This will ensure the 1st Marine Division remains prepared to fight and win amidst an increasingly complex operating environment.”